A new build underfloor heating system is easiest to get right before the slab is poured, not when the floor finishes are being selected. This new build UFH specification example shows how a water-based system could be set out for a typical UK property, from insulation and pipe spacing through to manifolds, controls and commissioning.

It is a worked specification, not a substitute for a room-by-room heat-loss calculation. Window areas, construction build-up, air-tightness, design temperature and the chosen floor covering all affect the final design. A competent UFH supplier should use the project drawings and heat-loss figures to confirm outputs, circuit lengths and flow temperatures before materials are ordered.

Why UFH specification matters in a new build

New-build properties are well suited to water underfloor heating because the floor construction can be designed around the system from the outset. There is usually room for insulation, pipework and screed without the compromises common in retrofit work. The result can be an even, low-temperature heat source that works particularly well with a heat pump or modern condensing boiler.

The specification matters because UFH is not simply pipe laid in a floor. A system with inadequate insulation loses heat downwards. Circuits that are too long can be difficult to balance. Wide pipe centres may leave a room short of output near large areas of glazing. Equally, specifying unnecessarily close centres everywhere adds material and installation time without always improving comfort.

The aim is to achieve the required room temperature at the lowest practical water temperature. That supports efficient heat-pump operation, reduces boiler cycling and gives the floor a more consistent surface temperature.

New build UFH specification example: 180m² detached house

This example assumes a two-storey, 180m² detached house with a ground-floor heated area of 95m². The ground floor has a concrete slab, insulation below the screed, and a 65mm sand and cement screed. The first floor uses radiators in bedrooms, although upper-floor UFH could be specified where joist or overlay-board construction is appropriate.

The ground floor includes an open-plan kitchen, dining and living area, utility, hallway, cloakroom, study and bathroom. The heat source is an air source heat pump designed to operate efficiently at low flow temperatures. Individual room heat losses have been calculated to the relevant design conditions before the pipe layout is produced.

Floor build-up

A typical ground-floor build-up could be specified as follows:

  • Structural concrete slab prepared to the project design.
  • Suitable damp-proof membrane where required by the building design.
  • Floor insulation sized to meet the project’s thermal requirements and current Building Regulations.
  • Perimeter edge insulation around external and internal walls, columns and fixed upstands.
  • UFH pipe fixing system, such as clip rails, castellated panels or staples fixed into compatible insulation.
  • 16mm oxygen-barrier UFH pipe.
  • 65mm sand and cement screed, or an alternative proprietary screed system installed to its manufacturer’s required depth.
  • Final floor finish, selected with its thermal resistance in mind.

The insulation thickness cannot be copied blindly from another project. It depends on the floor’s calculated U-value, the insulation material and the overall construction. What should not be overlooked is the edge insulation. It allows for screed expansion and helps reduce heat loss at the perimeter, where walls and glazing can create greater demand.

Pipe layout and spacing

For this property, 16mm pipe at 150mm centres is a sensible starting point across most ground-floor rooms. It provides good output at low flow temperatures while keeping circuit lengths manageable. In higher-loss areas, particularly the perimeter of the open-plan room with large glazed doors, the design may reduce spacing to 100mm or 125mm for the first metre from the external wall.

The bathroom may also use 100mm centres to provide a warmer floor and faster response, provided the calculated output and floor finish support it. Hallways, utility rooms and cloakrooms are often suitable for 150mm to 200mm centres, but only if the heat-loss calculation confirms sufficient output.

Each circuit should be designed within the pipe manufacturer’s recommended maximum length. With 16mm pipe, many designs keep loops at roughly 80 to 100 metres, including tails to and from the manifold. Shorter, balanced circuits make commissioning more straightforward and reduce excessive pressure loss.

A possible circuit schedule for the 95m² ground floor is six circuits: two for the open-plan space, one for the kitchen area, one for the hallway and cloakroom, one for the study, and one for the utility and bathroom. This is illustrative only. Room shape, fixed kitchen units, island positions and manifold location can alter the best arrangement.

Avoid placing pipe under permanent kitchen units, fitted wardrobes or sanitaryware unless it is specifically required. Heating those areas offers little benefit and can complicate future fixings. Pipe routes should also be recorded and photographed before screed is installed.

Manifold, pump and heat-source connection

Locate the manifold centrally where practical, such as a utility cupboard or under-stairs services area. A central position shortens circuit tails and makes access easier for commissioning and future servicing. The manifold should be housed where it remains accessible, rather than boxed behind permanent joinery.

For this example, a six-port stainless-steel manifold with flow meters, isolation valves, fill and drain points, automatic air vents and actuator connections would suit the circuit arrangement. Flow meters allow the installer to set each loop to its design flow rate during balancing.

Where the UFH is supplied directly by a heat pump at a suitably low temperature, a dedicated mixing valve may not be necessary. This is often the preferred arrangement because it avoids mixing down water that has already been heated. However, the hydraulic design must confirm that the heat pump’s required flow rate, minimum system volume and circulation requirements are met.

A pump and mixing set may be appropriate where UFH is connected to a higher-temperature boiler circuit or forms one zone alongside radiators. The right approach depends on the heat source, emitter mix and controls strategy. It should be selected as part of the overall heating design, not added as a default accessory.

Controls and zoning for everyday comfort

The example property uses wired thermostats, with one thermostat per meaningful zone. The open-plan kitchen, dining and living area is treated as a single zone because it shares the same use pattern and open layout. The study, hallway, bathroom and utility are zoned separately where independent control is useful.

Each thermostat connects to a wiring centre, which controls the relevant thermal actuators on the manifold. The wiring centre can also provide a heat-demand signal to the heat pump or boiler. This prevents the heat source running solely because a different part of the system is calling for heat.

Do not over-zone a new build simply because it is technically possible. A separate thermostat for every small area can add cost and create competing heat demands. Larger spaces with similar occupancy and solar gain generally work better as one zone. Bathrooms may benefit from a dedicated zone, while a well-insulated cloakroom may not need independent control at all.

Smart controls can add scheduling and app-based adjustment, but they do not replace a sound system design. UFH responds more slowly than radiators, especially in a thick screed. In a highly insulated home, maintaining a steady background temperature is often more efficient and comfortable than using aggressive timed setbacks.

Floor finishes and output limits

The final floor finish must be considered at specification stage. Tile and stone have low thermal resistance and transfer heat effectively. Engineered timber, laminate, vinyl and carpet can all be compatible with UFH, but the manufacturer must approve the product for heated floors and state its maximum temperature limit.

Carpet and underlay together should have a low enough tog value for the calculated output. Thick rugs can restrict heat locally. Timber requires particular care with moisture content, screed drying and maximum surface temperature. These are not reasons to avoid UFH, but they are reasons to confirm the finish before the design is signed off.

Installation, testing and commissioning

Before screeding, every circuit should be pressure-tested in accordance with the pipe manufacturer’s instructions and kept under test while the screed is laid. The installer should label each loop at the manifold and retain an as-fitted layout showing circuit routes, pipe spacing and manifold connections.

The screed must be allowed to cure and dry properly before the system is brought up to temperature. Commissioning normally involves increasing the water temperature gradually, rather than applying full heat immediately. Once complete, the installer can balance the flow meters, check actuator operation and hand over thermostat settings to the homeowner.

For a project of this size, early coordination between the builder, screeder, electrician, plumber and UFH designer avoids costly delays. The Underfloor Heating Company can help turn drawings and heat-loss information into a practical material schedule, so the system arriving on site is suited to the build rather than based on a generic pack.

The best specification is the one that reflects the actual house: its insulation, glazing, heat source, floor finishes and how each room will be used. Get those decisions agreed before first fix, and the finished floor can deliver quiet, efficient comfort for years to come.